Carriage Road Townhomes – Seal Coat Project

Project: Carriage Road Townhomes – Seal Coat Project

Project Status: This project will begin on Tuesday as planned.

Project Update: No updates at this time 

Project Hours: For all project information, please click on the link below to download the project notice and sitemap.

Project Manager: Chris Soria – 760-294-4944

Click below to download a copy of the project notice and or sitemap:

carriage-road-townhomes-seal-notice-9-16
carriage-road-townhomes-seal-notice-map-9-16

Pointe Del Mar – Seal Coat Project

Project: Pointe Del Mar – Seal Coat Project

Project Status: Project is scheduled to begin Thursday, September 22 at 7:30 a.m.  

Project Update: No updates at this time 

Project Hours: For all project information, please click on the link below to download the project notice and sitemap.

Project Manager: Chris Soria – 760-294-4944

Click below to download a copy of the project notice and or sitemap:

pointe-del-mar-seal-coat-project-notice-9-16

pointe-del-mar-seal-phase-map-9-16

NEW UPDATE 9/19/16 – Otay 5 Master Association – Seal Coat Project

Project: Otay 5 Master Association  – Seal Coat Project

Project Status: This project has begun as scheduled. Download the project maps below to see where we are working each day during this project. PLAN AHEAD!

Project Update: Due to weather, today’s phase (Phase 7) has been delayed and will be completed at a later date (To be Determined).  Phase 8, scheduled for tomorrow, is still on track to be completed as planned. 

Project Hours: For all project information, please click on the link below to download the project notice and sitemap.

Project Manager: Chris Soria – 760-294-4944

Click below to download a copy of the project notice and or sitemap:

ResealingLetterSeptember12016
Otay 5 HOA – REVISED Seal Notice – 8-16

Otay 5 HOA Map Packet – Full Updated Version

NEW UPDATE Collage HOA – Asphalt Repair Project

Project: Collage HOA – Asphalt Repair Project

Project Status: Asphalt work has been completed.  Seal Coating is the next step of the process.  As far as aesthetics are concerned, the Seal Coat will address much of the concern (i.e. parking space striping, asphalt appearance uniformity, etc.).    

Project Update: General clean up and removal of onsite equipment has occurred.  Areas of pooling water have been addressed and potential remedies (where appropriate) will be established and communicated through the property manager.  As stated above, striping will be more uniform and complete once seal coating has been applied.  Temporary striping will be provided until then and should occur this week.   

**Thank you for your patience and understanding throughout the project.  We realize the inconvenience placed upon residents during a project of this scope.  Weather can often shift project dates and timelines so we greatly appreciate your flexibility.  Over time, as newly applied asphalt mends, the community will be in great shape.  Additionally, the application of seal coat will make the community look even more amazing than it already does!**

All notifications and site maps have been distributed to each residence, as well as posted at swimming pools and mailboxes and are available for download at the bottom of this page.  

Project Hours: For all project information, please click on the link below to download the project notice and sitemap.

Project Manager: Chris Soria – 760-294-4944

Click below to download a copy of the project notice and or sitemap:

college-hoa-ac-notice-8-16

college-hoa-ac-notice-sitemap-8-16

Stonegate

Project: Stonegate Homeowners Association  – Asphalt Sealcoating Project

Project Status: This project will begin on Wednesday, May 11th.

Project Update: Due to unforeseen delays related to the pre-sealcaoting cleaning today, Wednesday 5/11, sections originally planned to be open at 6:30 will be delayed until approximately 8-8:30PM. We apologize for the inconvenience.

Project Hours: For all project information, please click on the link below to download the project notice and sitemap.

Project Manager: Rich Simpson – 408-595-1573