Quietwood HOA – Concrete, Asphalt & Sealcoat Project

CONCRETE PROJECT – DETAILS

STARTS WEDNESDAY SEPTEMBER 4th 

GREEN AREASNO PARKING IN SPECIFIC PARKING AREAS – Wednesday, September 4 after 7:30 AM***

NOT ALL PARKING IS CLOSED TO RESIDENTS – PARKING CLOSURES ARE IN IMMEDIATE WORK AREAS ONLY)

Opens Tuesday, September 10 by 7:30pm – After the first day of paving project

  • GREEN AREAS — the contractor is repairing concrete near your parking spaces. Due to the high risk for damage to both your vehicle and the new concrete areas, the parking spaces will be closed for the times listed above.


ASPHALT PROJECT – DETAILS

RED AREA NO PARKING IN LOT– Tuesday, September 10th  after 7:30 AM

Opens that evening by 7:30pm

BLUE AREA NO PARKING IN LOT – Tuesday, September 17th after 7:30 AM

Opens that evening by 7:30pm

  • Lot sections will be closed to all vehicle traffic while crew is working and while the barricades are up.

RED AREA The Entire LOT 2 Section will be closed to all parking and vehicle traffic.  Please see site map. During the project, vehicle access to this area will not be possible until that evening.  The parking area outlined in yellow is closed to through traffic but open to parking only – Entry and Exit is closed during the project.

BLUE AREA – The bottom half of LOT 1 will be closed to all parking and vehicle traffic.  Please see site map – During the project, vehicle access to this area will not be possible until the that evening.

PROJECT INSTRUCTIONS:

Don’t Get Towed! Any vehicles left parked in parking areas after 7:00 on Thursday, Sept 20, will be towed at owner’s expense.  Tow trucks will be on-site and will begin removing vehicles at 7:30 am sharp without any additional warning.

  • Mark your calendars and plan ahead.
  • You will be able to access you home by foot during the project. Please ask crew is you need assistance.
  • Move your vehicles to a legal parking space outside of the community the night prior to work beginning.
  • Lot sections will be closed to all vehicle traffic while crew is working and while the barricades are up.
  • You will be able to access you home by foot during the project. Please ask crew is you need assistance.
  • Pardon Our Dust This work will create some degree of dust and noise.  Black Diamond Paving, The Association or its Manager will not be liable for any cleaning of personal property due to the nature of the work.  If you are concerned about your vehicles getting dirty,  move it out of the work area to a legal parking space away from the work area.
  • Pay Attention and Read all No Parking Signs
  • Do not attempt to drive through closed work areas. It is both dangerous to you and will damage the new work. Residents who disregard closed areas and cause damage to any part of the new work will be financially responsible for any required repairs.

SEALCOAT PROJECT IS SCHEDULED TO START ON MON OCT 14th & WED OCT 16th – A NEW NOTICE WILL BE POSTED ON YOUR DOORS ONE WEEK PRIOR TO THE START OF THE PROJECT

BLUE PHASE: Monday Oct 14, Closed at 7:30am. re-Opens Oct 15, 9:30am 

YELLOW PHASE: Wednesday Oct 16, Closed at 7:30am . re-Opens Oct 17, 9:30am


YOUR PROJECT MANAGER:

Primary: Chris Soria
 Csoria@blackdiamondpaving.com
Sr. Project Consultant
Cell: 510.366.4204